The biogas installation at Pronk in Warmenhuizen, the Netherlands initially contained a 190 kWe CHP unit. Immediately after the startup, the istallation is expanded with a second  CHP unit of 190 kWe.

A year later, an additional digester and a 340 kWe CHP unit was placed to increase the capacity of the plant.

Unique about the biogas plant at Pronk is that low-grade co-materials are digested. The company uses cutting vegetable waste from a vegetable processor in the area as an input product for the digester. The solid feeding input system placed by HoSt is suitable for the shredding and processing of such input streams.

FASES DEL PROYECTO

Inicio de la construcción Fase 1: junio de 2006 Fase 2: marzo de 2007
Puesta en marcha Fase 1: noviembre de 2006 Fase 2: septiembre de 2007

ESPECIFICACIONES

Capacity 19 000 toneladas/año
Insumos Estiércol de ganado con maíz y residuos vegetales
Digestor(es) Fase 1: 1 x 1530 m³ Fase 2: + 1 x 1530 m³
Posdigestor(es) 1 x 4525 m³ + 4500 m³ después del almacenamiento
CHP Fase 1: 2 x 190 kWe Fase 2: + 1 x 340 kWe
Insumo de alimentación sólida Depósito de mezcla y dosificación de 60 m³ con tornillos de entrada
Prealmacenamiento/entrada Fase 1: estiércol de establos Fase 2: 2 x 70 m³ de depósitos de alimentación líquida

CARACTERÍSTICAS

  • Digestión de comateriales de baja calidad y bajo coste, tales como los residuos vegetales del entorno de la empresa.