In Kraslava, an old boiler system is replaced by a wood-fired boiler. This boiler is integrated with an existing steam turbine.
PROJECT MILESTONES |
|
Start construction | August 2007 |
Start-up / First Fire | April 2008 |
SPECIFICATIONS |
|
Wood storage | 400 m³ |
Fuel supply system | Feeds three boilers (of which 2 existing boilers) |
Furnace | Fresh wood chips with 30-55% moisture |
Flame tube boiler | 9 MWth, 15 barg /250°C |
CHARACTERISTICS |
|
|