Pig innovation centre Sterksel is, in cooperation with the Wageningen University and Research Centre (WUR), a research and innovation centre for renewable energy and pig farming. A biogas plant was already built, after which HoSt built a new digester with a solid feeding system and CHP unit. This new digester is integrated with the existing plant. HoSt has added a new control system so that the whole system is easier to operate. The plant produces 2.9 million kWh electricity per year.

PROJECT MILESTONES

Start Construction November 2008
Startup April 2009

SPECIFICATIONS

Capacity 40,000 m³/year
Input 50% pig manure; 50% residual
Digester(s) 1 x 2,200 m³
CHP(s) 1 x 364 kWe
Pre-storage/receipt Linking with existing installation
Solid Feeding input 30 m³ mixing/dosing bin with input screws

CHARACTERISTICS

  • Expansion of existing biogas plant
  • New higher-level controller for entire plant

More information

Do you want to receive more information about our biogas plants or do you want to know what HoSt can do for you? Don’t hesitate to contact us through [email protected] or call us on +31 (0)53 – 460 90 80.